Septic rules for a Lake of the Ozarks home

Who issues septic permits around the Lake, why lakefront lots don't get the acreage exemption, the state setbacks, and what to sort out before you hire a septic installer or buy a Lake house.

Before you call

Know which county your property is in, whether it is on a city sewer or sewer district, and if the lot touches the Lake. Ask the installer if they are registered with the county and the Missouri Department of Health and Senior Services, and who orders the soil test.

A bulldozer and dump truck grading a steep home site above Lake of the Ozarks.
Photo by Bill Kuykendall for the EPA DOCUMERICA project, July 1973, public domain, cropped; digging a home site above the Lake at Sunrise Beach, not a service provider. Photo credits

If your Lake house isn't on a city sewer or a sewer district, the septic system falls under county or state rules, and lakefront lots get the least room for exceptions. Missouri law can exempt single-family lots of three acres or more from the state septic rules, but that exemption does not cover lots next to a lake run by a public utility. Ameren runs Lake of the Ozarks under its federal license for Bagnell Dam, so plan on a permit before you install, replace or repair a system on a lakefront lot. Who issues that permit depends on the county.

Find out who issues your permit

The Missouri Department of Health and Senior Services keeps a county lookup of who handles onsite sewage permits, and it says work should not start until a permit is issued or an exemption is confirmed. In Camden County it is the Camden County Wastewater Department under a county ordinance. In Morgan County it is the Morgan County Health Center under a county ordinance. In Miller County the state health department handles it from Jefferson City. Inside a city limit, check with the city first, since some cities defer back to the state. The Camden ordinance does not apply to property that drains to a sewer. Morgan County requires a permit before construction or major repair for single-family homes on lots under five acres and for any lot next to a lake regulated by a public utility or the Corps of Engineers.

  • Which county and permit office covers my property?
  • Is the house on a city sewer or sewer district, or on its own system?
  • Does my lot border the Lake, and does that change what permit I need?
  • Will you pull the permit, or do I apply myself?

Camden County: the permit steps

Camden County requires a permit for new systems, replacements of the tank or laterals, and repairs. That covers residential lots under three acres and every residential lot adjoining the Lake, no matter the size. A soil morphology test comes first, and the county ordinance says the soil report can't be based on a percolation test. The application and system design go to the Wastewater Department for review against state and county minimums. A county inspector visits the site before the permit is issued, and the site, system and tank have to be marked with flags or paint. The permit is good for one year and gets posted on the property during construction. The installer must be registered with the county and the state, though a property owner may install or replace a septic tank themselves with a permit. If you need an exception, the county's variance board meets on the second and fourth Wednesday of the month.

  • Are you registered with Camden County and the state?
  • Who is doing the soil morphology test, and is it done before the design?
  • Will you mark the system and tank for the county site visit?
  • Can the job be finished inside the one-year permit?

Setbacks from the Lake and your well

State rules set minimum distances for septic tanks and disposal areas, and a county can be stricter. The state table calls for 50 feet from a classified stream, lake or impoundment for both the tank and the disposal area. A private well needs 50 feet from the tank and 100 feet from the disposal area. Property lines need 10 feet, and the building foundation needs 5 feet from the tank and 15 feet from the disposal area. Steep, narrow Lake lots can make those distances hard to fit. Ameren also does not allow individual wastewater systems inside its project boundary along the shore without its approval, and it does not allow toilets or showers on docks.

  • Where does the 50-foot setback from the Lake start on my lot?
  • Is my well far enough from the tank and the lateral field?
  • Does this design fit my lot, or will it need a variance or an advanced system?

Remodeling, adding on or buying a Lake house

In Camden County, a state registered inspector has to inspect the septic system before Planning and Zoning issues a building permit to remodel, rebuild or add on, unless the system has a valid operating permit. If you're buying, the state health department says local agencies mostly no longer inspect systems for real estate sales, so the assessment is done by a private inspector licensed by the state. An inspection includes a water volume test of the soil treatment area. An evaluation checks the tanks and looks for signs of failure, but does not test the soil treatment area. Copies of the report go to the state and the local agency. State rules don't make you bring an older system up to current standards just to sell, but local rules can be stricter, and a lender may require a certain type of report.

  • Do I need a full inspection or an evaluation for this sale or loan?
  • Is the inspector licensed by the Missouri Department of Health and Senior Services?
  • Will a planned addition or remodel trigger a septic inspection first?
  • If the report finds problems, does the repair need a permit?

Repairs, advanced systems and what the county can require

Camden County lets an emergency repair start after the Wastewater Department gives verbal consent, as long as the permit application follows within five working days. If the county finds a malfunctioning system or a nuisance, it can require the repair within 30 days, stretched to 60 if weather or finding a contractor gets in the way. Advanced systems installed on or after January 1, 2011 need an operating permit, and renewing it takes proof of a current maintenance agreement. New and repaired systems in Camden County must use poly, fiberglass or concrete tanks, with manhole access to the inlet and outlet and risers when the tank top is more than six inches below grade. Composting toilets are not allowed on property adjoining the Lake.

  • Is this an emergency repair, and have you called the county for consent?
  • Does my system have an advanced component that needs an operating permit?
  • Who will hold the maintenance agreement, and what does it cover?
  • Will the new tank have risers to grade?

Common questions

Do I need a septic permit on a big lakefront lot?

Usually yes. The three acre exemption in state law does not apply to lots next to a lake run by a public utility, and Camden County requires a permit for every residential lot adjoining the Lake regardless of size. Confirm with your county permit office before work starts.

How far does a septic tank have to be from the Lake?

The state minimum is 50 feet from a classified lake or impoundment for both the tank and the disposal area, and counties can be stricter. Ask your county office how the distance is measured on your lot.

Can I put in my own septic system?

In Camden County, a property owner can install or replace a septic tank with a permit, but the rest of the system has to be done by a contractor registered with the state and the county. Check with your county office for other areas.

How do I reach the Camden County Wastewater Department?

The office is at 186 Ha Ha Tonka Cut Thru in Camdenton, open Monday through Friday from 8 a.m. to 4 p.m., at 573-317-3810. The county lists a separate sewage complaint line at 573-317-3821. Forms are on the county's waste water page: https://camdencountymo.gov/departments/waste-water/

Can Lake Shortlist get my permit or pick an installer for me?

No. We list businesses and the questions worth asking. Confirm the rules for your property with your county permit office or the state health department.

Find businesses for this project

Read the stated jobs and service area, then build a comparison of up to three.

Related planning guides

Ready to describe your project?

Describe the work once. Lake Shortlist will review your request and may follow up with you. Your request stays with Lake Shortlist; nothing is automatically sent to a business.

Free to submit. A request does not guarantee a quote or a business’s availability.

Describe your project
Sources & editorial notes

Checklist questions are our editorial suggestions. This is not a personal-use testimonial, technical design, price quote or finding that any listed business is best. Confirm current requirements and project details directly.

No business paid for inclusion in this guide. Lake Shortlist is operated by Mason Bennett, who also owns Hollerback. Marketing services cannot buy editorial selections. Correction and dispute information.